Two 100-ton ultra-thin hydraulic jacks are placed on the single-piece beam, and mechanical support is used as a temporary support tool after the lifting is in place. According to the collection and analysis of technical parameters such as bridge data and construction plan, it was finally decided to use two sets of twenty-four-point intelligent control synchronous lifting hydraulic systems for synchronous control.